960MW offshore wind farm targets commercial operation in late 2028
ScottishPower Renewables (‘SPR’) has completed a subsea drilling and duct pull-in operation at its £4 billion East Anglia 2 offshore wind farm.
The company said the two cable ducts are the world’s longest continuous single sections of extruded polyethylene and will provide a protected pathway for the 960MW project’s high-voltage export cables.
It added that the ducts, at just under 1,800 metres long and 800mm in diameter, form the UK’s largest electricity transmission landfall of its kind based on the combination of those dimensions.
The ducts were installed beneath the Suffolk coastline and seabed using horizontal directional drilling (HDD), with rigs working onshore and offshore simultaneously.
The technique creates an underground bore without digging up beaches, dunes, cliffs or coastal habitats, minimising disruption to the environment and sensitive landscapes.
The works form part of the East Anglia TWO civil engineering programme being carried out by principal contractor OCU Group, with support from its subsidiary Peter McCormack & Sons.
The contract is supporting more than 80 jobs during construction.