Danish developer hails ‘incredible feat of engineering’
Orsted has installed the second and final offshore converter station (OCS) at the 2.9GW Hornsea 3 wind farm off east England.
Heerema was responsible for the transport and installation of the topside and its jacket foundation.
The OCS was built by Aibel in Map Ta Phut, Thailand, before sailing 13,000 nautical miles to Haugesund, Norway, for the installation and commissioning of high voltage equipment by Hitachi.
The structure stands at a total height of 70 metres above sea level which is 1.2 times higher than the Leaning Tower of Pisa.
The achievement follows the installation of the first OCS in March.
Hornsea 3 Managing Director Luke Bridgman said: “Adapting these massive structures to the specifics of their underwater sites and then successfully installing them is an incredible feat of engineering and a testament to the high level of collaboration across many different companies.
Altogether, the design, transport and installation of our offshore converter stations took four and a half years and many thousands of skilled workers.”